Agricultural product processing logistics project warehouse officially put into use

Agricultural product processing logistics project warehouse officially put into use

Summary

The logistics park warehouse project, consisting of three warehouses, B7, B8, and B9, has a total construction area of approximately 17100 square meters and a building height of 11.2-11.9 meters. It belongs to a large-span steel structure factory

Agricultural product processing logistics project warehouse  officially put into use

The general contracting project for the warehouse engineering of agricultural product processing logistics project (referred to as the "Logistics Park Warehouse Project") has passed the completion acceptance and is officially put into use. Our company fully leverages its industrial synergy advantages and actively promotes civil construction and steel structure installation projects, achieving efficient and high-quality construction in 8 months.

The logistics park warehouse project, consisting of three warehouses, B7, B8, and B9, has a total construction area of approximately 17100 square meters and a building height of 11.2-11.9 meters. It belongs to a large-span steel structure factory.

The B7 warehouse has a span of 36 meters and is currently the largest steel structure factory building in the local area. The total weight of the warehouse steel components (including purlins) is approximately 622 tons, with 134 steel columns and 252 steel beams.

To ensure the smooth progress of steel structure construction and installation, the project adopts the construction method of "factory processing, on-site assembly, and segmented lifting" according to the on-site construction conditions of the warehouse, fully leveraging the convenient characteristics and advantages of prefabricated structure construction, and quickly building prefabricated components on the construction site like "building blocks".